Upgrading of Local Access Road from Brgy. Bani to Brgy. San Vicente
PROJECT PROFILE
Project Title | UPGRADING OF LOCAL ACCESS ROAD (BANI – SAN VICENTE) FROM BRGY. BANI TO BRGY. SAN VICENTE |
Description of Project | Concreting of Municipal Gravel Road 200mm x 5.00m x 520m (approx) |
Funding Year | 2020 |
National Subsidy (Original Allocation) | 5,015,000.00 |
Type of Project | ROADS AND BRIDGES |
Sub Type of Project | ACCESS ROAD |
Procurement Type | Infrastructure |
Exact Location | Brgy. San Vicente to Brgy. Bani, Tinambac, Camarines Sur |
Beneficiaries | 1162 |
Status | COMPLETED |
IMPLEMENTATION INFORMATION
National Subsidy (Cancelled Allocation) | Php 0.00 |
National Subsidy (Revised Allocation) | Php 5,015,000.00 |
National Subsidy (Reverted Amount) | Php 0.00 |
LGU Counterpart/Cash Equity (Original Allocation) | Php 0.00 |
LGU Counterpart/Cash Equity (Cancelled Allocation) | Php 0.00 |
LGU Counterpart (Reverted Amount) | Php 0.00 |
LGU Counterpart/Cash Equity (Revised Allocation) | Php 0.00 |
Total Project Cost | Php 5,015,000.00 |
Implementing Unit | Municipal LGU |
Mode of Implementation | Contract |
CONTRACT DETAILS
Name of Contractor | RD Dayao Aggregate & Construction Supply |
Office Address | Zone 4 Del Pilar, San Fernando, Camarines Sur |
Date of Perfection of Contract | 2021-07-10 |
Date of Receipt of Notice to Proceed | 2020-10-28 |
Contract Amount | Php 5,014,919.38 |
Contract Duration | 120 |
Intended Completion Date | 2021-07-10 |